INTRODUCTION

The Pradhan Mantri Gram Sadak Yojana (PMGSY) was announced by the Prime Minister on 15th August, 2000 and the Scheme was launched on 25th December, 2000. The Primary source of funding for the Programme is from the Cess on High Speed Diesel, 50% of which is earmarked for Rural roads. The Pradhan Mantri Gram Sadak Yojana has been formulated as an Anti-Poverty Programme, focusing on providing connectivity to unconnected rural Habitations in order to enable access to economic and other essential services.

The Programme is executed by State Government Agencies in a Project Mode. Detailed guidelines have been issued for the PMGSY Scheme and a separate Rural Roads Manual has also been published on the technical aspects of Rural Roads construction.
 

ABSTRACT - PMGSY (Progress ending 31.07.2021)

PHASE

No. of Packages

No. of Roads

Total Length

Length Completed

Expenditure
(In lacs)

No. of Roads Completed

Remarks

Phase - I 16 86 166.24 116.24 2269.62 86 Completed
Phase - II 45 229 449.43 449.43 6505.13 229 Completed
Phase - III 22 114 223.72 207.29 3157.96 103 Completed (11 no. works dropped)
Phase - IV 31 59 419.47 418.51 7647.67 58 Completed (1 no. work dropped)
Phase - V 17 17 272.41 272.21 7979.00 17 Completed
Phase - VI 102 102 1252.95 1252.95 43361.34 102 Completed
Phase - VII 63 63 763.90 763.90 35060.89 63 Completed
Phase - VIII 70 70 923.92 918.23 35143.24 70 Completed
Phase - IX
36 36 499.37 490.21 22004.47 36 Completed
Phase - X 61 61 717.06 715.92 31788.00 61 Completed
  Phase - XI
(Batch 1)
101 124 637.64 637.64 30093.66 124 Completed
Phase - XI
(Batch 2)
45 46 455.24 452.94 23526.95 46 Completed
Phase - XII 48 48 173.46 173.46 7832.88 48 Completed
PMGSY-II 130 130 1342.82 1330.79 74219.79 130 Completed

Formats - |Quarterly| |Half Yearly| |Annually|
|
Joint Inspection Format| |Maintenance Inspection Format| |SE Inspection Format| |ATR Format|

Draft Policy PMGSY-III Colour Scheme for updation of Core Network Minutes of Meeting dated 09.04.2018
SQC for Punjab State PMGSY-II Road List Various Categories Road Length in the State
  PMGSY-III (Training 14.5.2018 Presentation)
Preparation / Updation of DRRP
 

 
Rural Road Project II (with Assistance of World Bank)
  IMPLEMENTATION OF ESMF
  1. PUBLIC DISCLOSURES
 
1.
Executive Summary
 
2.
Vulnerability Framework
 
3.
Social Management Framework RRP-II
 
4.
Enviroment and Social Management Framework
 
5.
Enviroment Code of Practice (ECoP)
 
6.
Social Management Framework
 
7.
Format ESMF for Border Road Corridor *
 
8.
Guideline for GRM (Grievance Rederessal Mechanism)
 
9.
Letter regarding institutionalization of GRM to Executing Agencies
 
10.
Name of designated Social/Environment Officers of PIUs
 
11.
List of GRC Members
 
12.
Template ESMF - Phase-XI
 
13.
Implementation of GRM
 
14.
Reminder for Preparation of ESMF

  2. PMGSY AUDITED BALANCE SHEETS
  1. Audited Balance Sheets Program Funds 2020-21
2. Audited Balance Sheets Admin Funds 2020-21
  3. Audited Balance Sheets Program Funds 2016-17
4. Audited Balance Sheets Admin Funds 2016-17

  3. DEDICATED OFFICERS
 
ITNO (Information Technology Nodal Officer for PMGSY Scheme)

Sh. Harjinder Singh
Contact Details : Off : 0172-5134631
Mob. : 9515216103
Email : sde3.prbdb (@) punjab.gov.in,

PMGSY Government of India Website |pmgsy.nic.in|